Any system for monitoring project performance should provide project manager and stakeholders with the ability to answer and which question seemed not to be relevant?

  • A. What is the current status of the project in terms of schedule and cost?
  • B. How much will it cost to complete the project?
  • C. Does your organization have capacity assessment plan?
  • D. When will the project be completed?

Answer: Option C