What is a project scope?
What is a project scope? A. Refers to all the work involved in creating the products of the project and the processes used to create them. B. It defines what is or is not to be done C. Refers to…
What is a project scope? A. Refers to all the work involved in creating the products of the project and the processes used to create them. B. It defines what is or is not to be done C. Refers to…
An activity that has more than one activity immediately following it (more than one dependency arrow flowing from it), is called: A. Burst activity B. Merge activity C. Parallel (concurrent) activities D. Even Answer: Option A
Activities that can occur independently and, if desired, is called: A. Merge activity B. Parallel (concurrent) activities C. Even D. Burst activity Answer: Option B
A point in time when an activity is started, is called: A. Merge activity B. Parallel (concurrent) activities C. Even D. Burst activity Answer: Option C
An activity that has two or more preceding activities on which it depends, is called: A. Merge activity B. Parallel (concurrent) activities C. Even D. Burst activity Answer: Option A
Which activities can occur while the another activity is taking place? A. These activities are called predecessor activities B. These activities are called successor activities C. This activity is called critical path D. This is known as a concurrence or…
Which activities must immediately follow the another activity? A. These activities are called predecessor activities B. These activities are called successor activities C. This is known as a concurrence or parallel relationship D. This activity is called critical path Answer:…
Which activities must be completed immediately before one activity? A. These activities are called predecessor activities B. These activities are called successor activities C. This is known as a concurrence or parallel relationship D. This activity is called critical path…
What is not listed as basic rules to follow in developing Project Networks? A. Project network is simple and not necessary B. Networks typically flow from left to right. C. An activity cannot begin until all preceding connected activities are…
Which one is best explained the project activity? A. The project activity has to calculate the acting time spend B. The project activity has to calculate risk C. The project activity has to calculate the acting time and related time…