Given the following sets of test management terms (v-z), and activity descriptions (1-5), which one of the following best pairs the two sets?

v – test control w – test monitoring x – test estimation y – incident management z – configuration control 1 – calculation of required test resources 2 – maintenance of record of test results 3 – re-allocation of resources when tests overrun 4 – report on deviation from test plan 5 – tracking of anomalous test results

  • A. v-3,w-2,x-1,y-5,z-4
  • B. v-2,w-5,x-1,y-4,z-3
  • C. v-3,w-4,x-1,y-5,z-2
  • D. v-2,w-1,x-4,y-3,z-5

Answer: Option C