If you have a project life of months, which is best described of how you divide timeframe to meet the theory in the Project Life Cycle?
- A. Defining is for 1 month, planning is ongoing for 20 months, executing is for 20 months and delivering is for 1 month
- B. Defining is for 2 to 3 months, planning is ongoing for 20 months, executing is for 20 months and delivering is for 2 to 3 months
- C. Defining is for 5 months, planning is ongoing for 10 months, executing is for 15 months and delivering is for 1 month
- D. Defining is for 10 months, planning is ongoing for 1 month, executing is for 15 months and delivering is for 1 month
Answer: Option B