In order to create a project monitoring system involves determining:
- A. What and where are the causes for cost or schedule overrun?
- B. What data to collect, how, when, and who will collect the data, How to analyze the data, How to report current progress to management
- C. What have we gotten for the dollars spent?
- D. If there is a cost overrun midway in the project, can we forecast the overrun at completion?
Answer: Option B