What are the sequence steps of measurement and evaluation of Project Performance?

  • A. Measuring progress and performance, Setting a baseline data comparing plan against actual, and taking action
  • B. Setting a baseline data, comparing plan against actual, and taking action, and measuring progress and performance
  • C. Setting a baseline data, measuring progress and performance, comparing plan against actual, and taking action
  • D. Comparing plan against actual, and taking action Setting a baseline data, measuring progress and performance

Answer: Option C