What are the sequence steps of measurement and evaluation of Project Performance?
- A. Measuring progress and performance, Setting a baseline data comparing plan against actual, and taking action
- B. Setting a baseline data, comparing plan against actual, and taking action, and measuring progress and performance
- C. Setting a baseline data, measuring progress and performance, comparing plan against actual, and taking action
- D. Comparing plan against actual, and taking action Setting a baseline data, measuring progress and performance
Answer: Option C