What is best described as the contingency plan?

  • A. An alternative plan that will be used if a possible foreseen risk event actually occurs.
  • B. A plan of actions that will reduce or mitigate the negative impact (consequences) of a risk event
  • C. An alternative plan that will be used if a possible foreseen risk event actually occurs and a plan of actions that will reduce or mitigate the negative impact (consequences) of a risk event
  • D. Changing the project plan to eliminate the risk or condition

Answer: Option C