What is best described as the contingency plan?
- A. An alternative plan that will be used if a possible foreseen risk event actually occurs.
- B. A plan of actions that will reduce or mitigate the negative impact (consequences) of a risk event
- C. An alternative plan that will be used if a possible foreseen risk event actually occurs and a plan of actions that will reduce or mitigate the negative impact (consequences) of a risk event
- D. Changing the project plan to eliminate the risk or condition
Answer: Option C