What is not listed as basic rules to follow in developing Project Networks?
- A. Project network is simple and not necessary
- B. Networks typically flow from left to right.
- C. An activity cannot begin until all preceding connected activities are complete.
- D. Each activity must have a unique identify number that is greater than any of its predecessor activities.
Answer: Option A