What is not listed as the concept of Agile Project Management?

  • A. Relies on incremental, iterative development cycles to complete less-predictable projects.
  • B. Is ideal for exploratory projects in which requirements need to be discovered and new technology tested
  • C. All plans must follow and cannot change
  • D. Focuses on active collaboration between the project team and customer representatives.

Answer: Option C