What is not listed for the project audit?
- A. Evaluate if the project delivered the expected benefits to all stakeholders. Was the project managed well? Was the customers satisfied?
- B. What and where are the causes for cost or schedule overrun?
- C. Assess what was done wrong and what contributed to success?
- D. Identify changes to improve are instruments for supporting continuous improvement and quality management.
Answer: Option B