What is not listed to explain the project audit?
- A. Project audits include reassessment of the project’s role in the organization’s priorities. Project audit include a check on the organizational culture to ensure it facilitate the type of project being implemented
- B. Project audits assess if the project team is functioning well and is appropriately staffed.
- C. Audits of project in process should include a check on external factors that might change where the project is heading or its importance — for example: technology, government laws, competitive products, etc.
- D. Project audit is to assess the management and leadership of the organization
Answer: Option D