Which are the approaches to constructing project network?

  • A. Activity-on-Node (AON) and Gantt Chart
  • B. Activity-on-Arrow (AOA) and Gantt Chart
  • C. Pert Chart and Gantt Chart
  • D. Activity-on-Node (AON) and Activity-on-Arrow (AOA)

Answer: Option D