Which are the approaches to constructing project network?
- A. Activity-on-Node (AON) and Gantt Chart
- B. Activity-on-Arrow (AOA) and Gantt Chart
- C. Pert Chart and Gantt Chart
- D. Activity-on-Node (AON) and Activity-on-Arrow (AOA)
Answer: Option D
Which are the approaches to constructing project network?
Answer: Option D