Which of the following activities should be performed during the selection and implementation of a testing tool?

a. Determine whether the organisation’s existing test processes needs to change. b. Conduct a pilot implementation. c. Implement the selected tool on a project which is behind schedule to save time. d. Identify coaching and training requirements for the use of the selected tool

  • A. a, b and c
  • B. b, c and d
  • C. a, c and d
  • D. a, b and d

Answer: Option D