Which of the following are key success factors to the review process?
- A. Review time is allowed in the test execution schedule, process improvement is recognised in the follow up meeting and the objective is always to find defects
- B. Each review has a clear objective, the right people are involved, training is provided in the review technique and management fully supports the process
- C. Participants are trained, all review meetings are time boxed and moderators are project managers
- D. Every team member will be involved, all review techniques are used on every work product and test managers control the review process
Answer: Option B