Which of the following statements is a valid objective for testing?

  • A. To determine whether enough component tests were executed within system testing.
  • B. To find as many failures as possible so that defects can be identified and corrected.
  • C. To prove that all possible defects are identified.
  • D. To prove that any remaining defects will not cause any failures.

Answer: Option B