Which one is best explained the risk management strategy?

  • A. The project may need to consider to high staff with high motivation
  • B. The project must wait until the risk disappear by itself and then the project can start
  • C. The project manager is the only person who is responsible for all risks
  • D. Before building the warehouse, the project needs to invest in building infrastructure surrounding to prevent from flood especially in the rainy season

Answer: Option D