Which one of the following best describes risk-based testing?

  • A. Testing as much of the system as possible in the time available
  • B. Targeting testing at the more critical areas of the system
  • C. Making full use of formal test case design techniques
  • D. Fixing as many defects as possible before go-live

Answer: Option B