Which statement is best explained the comparing plan against actual?

  • A. It derives from the cost and duration information found in the Work Breakdown Structure database and time sequence in the network and resources scheduling decisions.
  • B. Periodic monitoring and measuring the status of the project allow for comparison of actual versus expected plan
  • C. If deviation from plan is significant, corrective action will be needed to bring the project back in line with the original or revised plan
  • D. Time and budgets are quantitative measures of performance and meeting customer technical specification is qualitative

Answer: Option B