Which statement is best explained the measuring progress and performance?
- A. Time and budgets are quantitative measures of performance and meeting customer technical specification is qualitative
- B. Periodic monitoring and measuring the status of the project allow for comparison of actual versus expected plan
- C. If deviation from plan is significant, corrective action will be needed to bring the project back in line with the original or revised plan
- D. It derives from the cost and duration information found in the Work Breakdown Structure database and time sequence in the network and resources scheduling decisions.
Answer: Option A