Which statement is true about the project cost?
- A. The high cost to fix risk event is at the delivering stage
- B. The high cost to fix risk event is at the beginning and planning stages
- C. The high cost to fix risk event is at the executing stage
- D. We do not need to fix risk risks because when the project is finished, risks are disappeared so that we do not need to spend money for it
Answer: Option B